This is a 30-day public comment period for the review of VoltaGrid's - Electric Generation Plant draft air permit, technical support document, and notice of construction (NOC) application with associated documents.
We propose to approve VoltaGrid - Electric Generation Plant (VoltaGrid) air quality notice of construction (NOC) application
VoltaGrid submitted a NOC application for their site location east of Road O NW and north of Road L NW, in Quincy. Parcel 0401414050 at Section 4, Township 20 N, Range 24 E. VoltaGrid supplies ready to use affordable, and clean power and fuel solutions for remote and grid-parallel applications.
VoltaGrid is proposing to install 14 prime power natural gas generators, 30 megawatts (MWe) total power supply. VoltaGrid plans to install on the generators, selective catalytic reduction controls for nitrogen oxides and an oxidation catalyst controls for carbon monoxide (CO) and volatile organic compounds (VOCs). Emission increases from this project include:
41 tons per year carbon monoxide (CO)
10 tons per year volatile organic compounds (VOCs)
8.8 tons per year particulate matter (PM)
8.7 tons per year nitrogen oxides (NOx)
6.3 tons per year formaldehyde (CH₂O)
6.2 tons per year sulfur dioxide (SO₂)
We determined this proposal satisfies the requirements of Chapter 173-400 WAC. We plan to approve the application.
Tentative online public hearing: Monday, August 10, 2026, 6 p.m.
(if requested by July 22, 2026, 11:59 p.m.)
We will hold a public hearing if there is significant public interest. If we do not receive significant written requests for a public hearing by July 22, 2026, then the online public hearing will be cancelled. We will update this information by either cancelling the public hearing or with a link to the public hearing. If you request a public hearing, please tell us if you need interpretation in a language other than English.
Accessibility: To request ADA accommodation for the public hearing, email janice.batchelor@ecy.wa.gov by Wednesday, July 22, 2026. Or call 509-496-3003, 711 (relay service), or 877-833-6341 (TTY).
Contact information is necessary if you want to receive future notices or responses related to this topic.
Contact Information
*Indicates Required Fields
Thank you for subscribing to the VoltaGrid, Electric Generation Plant public comment period July 7, 2026, 12 a.m. - August 13, 2026, 11:59 p.m. mailing list.
Para asistencia en español: Servicios de Idiomas or AQoutreach@ecy.wa.gov.
This is a 30-day public comment period for the review of VoltaGrid's - Electric Generation Plant draft air permit, technical support document, and notice of construction (NOC) application with associated documents.
We propose to approve VoltaGrid - Electric Generation Plant (VoltaGrid) air quality notice of construction (NOC) application
VoltaGrid submitted a NOC application for their site location east of Road O NW and north of Road L NW, in Quincy. Parcel 0401414050 at Section 4, Township 20 N, Range 24 E. VoltaGrid supplies ready to use affordable, and clean power and fuel solutions for remote and grid-parallel applications.
VoltaGrid is proposing to install 14 prime power natural gas generators, 30 megawatts (MWe) total power supply. VoltaGrid plans to install on the generators, selective catalytic reduction controls for nitrogen oxides and an oxidation catalyst controls for carbon monoxide (CO) and volatile organic compounds (VOCs). Emission increases from this project include:
We determined this proposal satisfies the requirements of Chapter 173-400 WAC. We plan to approve the application.
Tentative online public hearing: Monday, August 10, 2026, 6 p.m.
(if requested by July 22, 2026, 11:59 p.m.)
We will hold a public hearing if there is significant public interest. If we do not receive significant written requests for a public hearing by July 22, 2026, then the online public hearing will be cancelled. We will update this information by either cancelling the public hearing or with a link to the public hearing. If you request a public hearing, please tell us if you need interpretation in a language other than English.
Accessibility: To request ADA accommodation for the public hearing, email janice.batchelor@ecy.wa.gov by Wednesday, July 22, 2026. Or call 509-496-3003, 711 (relay service), or 877-833-6341 (TTY).
Read project documents online.
Next steps
After the public period ends, we will:
Contact information is necessary if you want to receive future notices or responses related to this topic.